Bagamoyo Port: a chronology, 2013–present

Also known in investment literature as Mbegani deep-sea port. A $10 billion port on Tanzania's coast has been announced, suspended, revived, denied and re-signed across three presidencies since 2013. This page groups those thirteen years into four announcement cycles and links every dated claim to the source that supports it. As of 20 September 2026, no independent source confirms that physical construction has begun.

Thirteen years in four announcement cycles

Each cycle starts with an announcement, names someone who will pay for it, and ends a different way. The dates below are the boundaries of each cycle, not of the project.

How this page labels each dated entry. Every entry below carries exactly one of these four labels, and no others.

Announced
Stated publicly by a named party, and not yet verified to have happened.
Confirmed
Reported as having happened by a named source.
Denied
Publicly contradicted by a named official or body.
Unverified
Reported or expected, with no independent source confirming it.

Cycle 1, 2013–2019: announced with China and Oman, stopped by the next government

The original structure was a Chinese builder, an Omani sovereign fund, a $10 billion headline figure and a promise to finish within three years. It ended six years later, with Tanzania's ports authority saying the investors' conditions would deny the country the benefit of its own port.

Cycle 2, 2021–2024: revived under government leadership; the named investors leave

The second cycle dropped the 2013 financing structure and put the Tanzanian government in the lead. Note the order of the two 2022 entries below: the investors withdrew first, and the announcement of a 2023 start came a month later.

September 2022

Announced. A month after the withdrawal, TPA director general Plasduce Mbossa said construction would start in the next financial year — 2023 — without waiting for an investor: “Investors will join us on the way,” he told The Citizen. He also said the actual cost of building Bagamoyo was yet to be known and would be made public once preparations were complete. Construction did not start in 2023.

Cycle 3, February 2025: a Saudi takeover reported, then denied three times in twelve days

The shortest cycle here: reported, denied by the Tanzanian government, denied by the Saudi embassy, denied again by the ports authority, and superseded by three memoranda — all inside one month.

13 February 2025

Announced. The Saudi Press Agency quoted Hassan Al-Huwaizi, chairman of the Federation of Saudi Chambers of Commerce, as saying Tanzania had granted a Saudi company ownership and operating rights over Bagamoyo, as part of Saudi Arabia's East Gateway project. Photographs of Tanzanian officials with Saudi investors circulated as a signing ceremony.

Denied. The same day, a senior government official told Daily News the information was false: the meeting concerned a joint business plan, not a transfer of ownership, and no formal agreement had been signed.

24 February 2025

Denied. Briefing journalists in Dodoma, TPA director general Plasduce Mbossa said: “We have not signed any contract for the construction of Bagamoyo Port. What is currently being undertaken is a feasibility study review, following the suspension of the process years ago.” Several companies had expressed interest, he said, but what was being signed were memoranda of understanding, to open discussions (Daily News, 24 February 2025).

Cycle 4, from November 2025: an operator signs, and three start dates pass

This is the first cycle to name a company that actually runs ports rather than a sovereign fund or a state builder — the reason this project became worth tracking again. It is also the cycle in which three start dates have been announced and none independently confirmed.

December 2025

Confirmed. The TPA signed a memorandum of understanding with Africa Global Logistics (AGL) Tanzania Ltd, a subsidiary of MSC, to design, build and operate three new berths at Bagamoyo — “three modern berths out of the 28 planned for the port” — plus two at Dar es Salaam.

Mbossa signed for the TPA and Philippe Labonne for AGL; the deal was reported in the trade press the following week. Building the three berths was to take three years.

What was signed is a memorandum of understanding, not a construction contract — the same instrument the TPA had described ten months earlier as a way to open discussions.

January 2026

Announced. At the December signing Mbossa said: “We expect to begin construction of the three new berths at the Port of Bagamoyo early in January” (Daily News, 6 December 2025).

27 July 2026

Confirmed. This contradicts both announcements above. Mbossa told Daily News that the first phase — dredging the port basin, the shipping access channel and the initial berths — was scheduled to start “next month”, meaning August 2026. The December 2025 and January 2026 start dates therefore passed without the works they announced.

Two figures in that interview do not match the December 2025 signing: Mbossa put the port's eventual capacity at 38 berths, against the 28 in the AGL memorandum, and the first phase at about 26 trillion shillings. Both are in the table below.

20 September 2026

Unverified. Checked again on this date. No independent source confirms that dredging began in August 2026 as the TPA's own director general said it would. This entry has no link because it records the absence of a source, not a source: everything publicly available is either the November–December 2025 announcements or Mbossa's July 2026 statement, and nothing published in the first three quarters of 2026 reports work under way on the ground.

Every announced start date, and what followed

This is the pattern, without commentary. Each date in the first column links to the source that announced it.

Dates announced for starting or completing work at Bagamoyo, and their status as of 20 September 2026.
AnnouncedWork promised forWhat followed
2015Completion by 2018Project stopped in 2019
Nov 2017Operations 2020–2021Did not happen
Sep 2022Construction in 2023Did not happen
Nov 2025December 2025Not independently confirmed
Dec 2025January 2026Contradicted by the TPA in July 2026
Jul 2026August 2026Not independently confirmed

Six announced dates across eleven years. The confirmed record over the same period consists of one groundbreaking ceremony, one completed compensation programme, and four signed memoranda of understanding.

The figures the sources do not agree on

Three different dollar totals, two first-phase budgets and two berth counts are in circulation at the same time. No source consulted reconciles any of them. This page reports the disagreement rather than choosing a number.

Figures reported for the same project, side by side, as of 20 September 2026.
What is countedFigureWhere it comes from
Total cost, as first announced$10 billionThe 2013 agreement; still the most repeated figure (The Citizen, 2019)
Total costTZS 23 trillionGiven as the shilling equivalent of $10bn (The Citizen, Aug 2022)
Total cost$10 billion“If completed, the $10 billion Bagamoyo port project”, reporting the AGL deal (The Maritime Executive, 21 Dec 2025)
Total cost$2.1 billion“The total investment earmarked for the full port development”, reporting the same deal eight days later (African Review, 29 Dec 2025)
Total cost$11 billionDredgeWire, June 2026
First phaseTZS 22 billion (about $9.3m)Berth foundations and access roads (Aphex)
First phaseAbout TZS 26 trillionDredging, access channel and initial berths (Daily News, Jul 2026)
Berths when complete28TPA director general at the AGL signing (Daily News, Dec 2025)
Berths when complete38The same official, eight months later (Daily News, Jul 2026)

Where a source gives a figure in shillings, this page reports it in shillings and does not convert it at a later exchange rate.

Who was going to pay, in order

  1. 2013–2019 — China Merchants Group and Oman's State General Reserve Fund. China was to build the port, Oman's fund to finance the industrial zone. The talks stalled in 2019 over the investors' conditions.
  2. 2022–2025 — the Tanzanian government itself. After the Chinese and Omani firms left the talks, the TPA said it would begin without an investor. No construction followed.
  3. February 2025 — Saudi Arabia, reported and denied. A reported acquisition under the East Gateway project was denied by the Tanzanian government, by the Saudi embassy and by the TPA within twelve days. Memoranda with Saudi, Chinese and Egyptian firms were signed the day after the last denial.
  4. December 2025 onward — Africa Global Logistics, a subsidiary of MSC. The first counterparty that operates ports rather than financing them. As of 20 September 2026 the arrangement remains a memorandum of understanding covering three berths.

The rail corridor, and the Egypt thread

Coverage often presents the port as a gateway to Zambia and the Democratic Republic of Congo over the existing TAZARA railway. There is no separately named “Bagamoyo corridor” scheme distinct from the port and that existing line: it appears as a connectivity argument, not as a funded programme with its own budget and timetable.

Announced. During President Abdel Fattah el-Sisi's state visit, Tanzania and Egypt proposed transport projects linking Bagamoyo Port with the Kwala Industrial Park and the standard-gauge railway network, and were reported to be in the final stages of establishing a Dar es Salaam–Cairo multimodal logistics hub.

As described in that same report, the hub links the port of Dar es Salaam to Egypt's Sokhna and Safaga ports — not Bagamoyo. This page does not count it as a Bagamoyo commitment until a source ties it to Bagamoyo specifically.

Where this fits on the rest of this site

Last substantive update: 20 September 2026. This page is reviewed at least every six months even when nothing has changed.